Subject of Work :
In the block Dock construction work ;
- 70.000 m3 sea bottom dredging
- 450.000 tons of 0-0,4 ton and 0-250 tons stone filling in the dredged area
- Construction and installation of 1.685 38-ton, 32-ton and 22-ton precast concrete blocks
- 900m coarse and fine coastal grading